Dreamstime M 162474409(1)
 

Eversource: COVID-19 Pandemic Among Drivers Delaying Massachusetts Project Completion

The projected total cost for the project remains $50.2m, while the total actual cost for the project as of May 31 was $46.2m, the company said

 
 

Announcements

 
Altoona Transmission Photo3 Websized
 

FirstEnergy Transmission Project Underway in Altoona

46-kV line will provide flexibility to the T&D system to quickly restore power to customers after service interruptions.

 
Advertisement
1594721866 Meyer Pi P724
Structures. Services. Solutions.
Through partnership with Formet, Meyer Utility Structures can provide both high and low pre-fabricated substation steel structures from A-frames, static masts and H-frames to bus supports, PT stands and switch structures. Click here to learn more.
 

 
Dreamstime M 77655987
 

I&M: Route Proposed For Approximate $12m Line In Indiana

The company said that construction on the project is expected to begin in summer 2021 and to conclude in late 2021

 
Advertisement
1594721581 Plh724
Complete Line Construction Solutions
PLH Group is a full service partner for the electric power delivery market, providing transmission, distribution and substation services, foundations and helicopter operations. Safety, expertise, and collaboration distinguish PLH Group’s solutions. Click here to learn more.
 

Advertisement
1589917636 Simple300250 Tstm Cat Spon
Eliminate direct 480 metering voltage
TSTM’s low voltage metering solutions reduce 480v metering voltage to safer levels which virtually eliminates meter/AMI failure, reduces liability, protects customer equipment, and increases revenue by cutting servicing costs. Click here to learn more.
 
 

Advertisement

 

Business & Technology

 
Dreamstime M 40976157

Digital Engineering Ltd Announces Contract With TransGrid Regarding Weather Effects On Network

This project will assist TransGrid, which operates the transmission network in the state of New South Wales, to fully operationalize its dynamic line rating system.

 
 
 

Construction Equipment & Services

 
Turnkey Contract Power Export Cables Scotland Seagreen Offshore Windfarm Project Cover
 

Nexans To Supply Power Export Cables for Seagreen Offshore Wind Project

Construction on the 1,075-MW project, which is located 27 km off the coast of Angus, will start next year.

 
 
Statnett Jul92020
 

North Sea Link On Schedule Despite COVID-19 Pandemic

Statnett and British company National Grid is building the NSL interconnector between Norway and the UK.

 
 

Sponsored Content

Sponsored
Tstm 3945 T Dworld
 

When You’re Smiling…

The Whole World Smiles With You!

 
Sponsored by TSTM, Inc
Tdworld 19255 Tstm Adapter With Meter Photo 1540 X 800 0
 

Transformer-Rated Meters in a Self-Contained Socket!

Go Low-voltage With Meter Adapters From TSTM.

 
 

Connect With Us

social icon   social icon   social icon   

This email is being sent to @{email name}@.

Please add news.endeavorb2b.com and mail.endeavorb2b.com to your address book or safe sender list to receive our emails in your inbox.

Unsubscribe | Manage Newsletter Subscriptions  | Forward to a Friend | Customer Service Center | Read Privacy Policy| Find Jobs

If this email was forwarded to you and you are interested in subscribing, please click here to sign-up.

If you have trouble with any of these methods, you can reach us toll-free at 800-547-7377.

Transmission and Distribution World
Endeavor Business Media
331 54th Avenue N.
Nashville, TN 37209